Tangeman
University Center
* Design -- Gwathmey Siegel & Associates
Architects of New York and local firm GBBN
Architects
* Cost -- $50.8 million
Joseph Steger Student Life Center
* Design -- Moore Ruble Yudell Architects and Planners of Santa
Monica
* Cost -- $26.2 million
Swift Hall Renovation
* Cost -- $11 million
Campus Recreation Center
Under construction, to be completed by spring 2006. New housing
scheduled to open in fall 2005
* Design -- Morphosis of Santa Monica, in partnership with KZF Inc.
* Cost -- $102.5 million
MainStreet Open Space
* Design -- Hargreaves Associates and local partners Glaserworks
* Cost -- $21.6 million
Infrastructure
Underground mechanical, plumbing and electrical utilities and
communication systems
* Cost -- $21.7 million
Total: $233.8 million
The majority of the cost of the MainStreet project is paid for
by student fees and the rest is supported by state funding, gifts and
rent.